Decision Room · Procurement and integrity
The Urgent Contract
After a cyclone, an official must restore services quickly without breaking procurement rules.
This is a hypothetical scenario created for learning. It does not describe any real incident.
The situation
A cyclone has damaged the power lines of a coastal district. As the Executive Engineer, you need transformers within a week. The normal tender process takes about six weeks. A supplier you have never worked with offers to deliver in four days at a price slightly below the market rate and asks for an advance payment of the full amount.
Your Chief Engineer says to give the order and regularise it later. A junior officer privately warns that the supplier has been blacklisted by another State, though he cannot show proof.
Questions
- Which provisions in procurement rules might allow quick action in an emergency?
- What risks arise from an advance of the full amount to an unknown supplier?
- How would you verify the supplier within the time available?
- How would you respond to the Chief Engineer, and in what form?
- What records would protect both the public interest and you?
Points to think about after you answer
Editorial discussion points for learners. They are not a statement by Mr. Azad.